1. A company uses the percentage-of-completion method to recognize revenue from its long term construction contracts and estimates percent completion based on expenditures incurred as a percentage of total estimated expenditures. A three-year contract for €10million was undertaken with a 30% gross profit anticipated. The project is now at the end of its second year, and the following end-of-year information is available:

The gross profit recognized in year 2 is closest to: